Q2

...

  • Electrical power infrastructure upgrades for NCI (ANU Building 143) and ANU south precinct
  • NCI data centre cooling system upgrades
  • Gadi system updates
  • Lustre file system updates (includes /scratch and all /gdata file systems)
  • Cloud system updates
  • Updates to ARE and data services

...

  • Run any significant Gadi jobs needed to support milestones or deadlines as soon as possible during April.
  • Back up or move any important data in /scratch directories to appropriate longer-term storage locations, e.g. project directories on /gdata before 30 April.
  • Pause any automated scripts used for routine tasks involving Gadi, /scratch, /gdata or cloud or data services, and develop a plan to restart these after completion of maintenance. 
  • Plan for interruption to any services which rely on Lustre file systems: /scratch, /gdata. 

...

Q1

NCI Q1 2024 Scheduled Maintenance
 
Date and duration: Thursday 1 February (8am - 6pm AEDT)


Systems affected:

...